Year completed: 2012

A35 Closure

In May 2012 the Highways Agency allowed its first ever daytime closure for routine maintenance on a national trunk road – a revolutionary idea piloted by SWH.


We suggested closing 8.5 miles of the A35 for a full 36 hour period to complete all necessary maintenance in one go, therefore avoiding several partial closures staggered over the year.  We put the proposition to the HA for the following reasons:
 

  • Less disruption over the year for the road user
  • Carrying out all activities independently would take 12 months, meaning several road closures and traffic management processes spread over the period
  • This ‘block’ method ensures less nightly closures. Major activities, such as surfacing, would have otherwise closed sections of the road for six nights
  • By closing the road, the number of live carriageway crossings would be reduced by 85%
  • This way of working creates a much safer environment for our operatives to work in
     

Maintenance works carried out by SWH during the closure included:

  • Surface treatment works
  • Patching
  • Re-surfacing
  • Landscape maintenance
  • Road marking
  • Drainage works
  • Sign repairs and cleaning
  • Road cleaning
     

The 36 hour closure was a complete success, thanks to thorough planning and effective communication with numerous organisations, including Devon, Somerset and Dorset County Councils with whom we worked closely. The work was completed within the specified time frame with no delays.

Local residents were also kept informed well in advance and many took the opportunity to undertake work to their properties at the same time. In many cases, works would not have been safe to complete whilst the road was open, such as painting fences by the roadside and jet-washing garden walls.

Before any work began, the section of the road was closed and two diversion routes were created. Another innovative aspect of the scheme was the placement of Hardstops around the closures, enabling local people to travel on short distances of the closure before carrying on with their journey. Each Hardstop was manned by an operative called a Gatesman who was available to assist and advise drivers as required.